Reactive power does no work but loads cables, transformers and switchgear – and is billed by the grid operator. How much capacitor rating is needed to reach a given power factor is a single formula.

Input

Grid operators usually require at least 0.90.

Result

Required compensation power
kvar
Apparent power before
kVA
Apparent power after
kVA
Relief on the supply
%

A guide, not a design to standard. The applicable standards and case-by-case verification govern.

Worked example

The default case the calculator starts with, worked through once. Change the values above and it recalculates immediately.

Inputs

Active power
150 kW
Present cos φ
0.75
Target cos φ
0.95

Result

Required compensation power
83 kvar
Apparent power before
200 kVA
Apparent power after
158 kVA
Relief on the supply
21.1 %

Formula

  • Qc = P · (tan φ₁ − tan φ₂)
  • φ = arccos(cos φ)
  • S = P / cos φ

Assumptions and standards

  • The calculation applies to the operating point you enter. With strongly varying load, an automatically controlled system is more suitable than fixed compensation.
  • With significant harmonic content – for example from drives – detuned capacitors are required, otherwise resonance can occur.
  • The relief figure refers to the apparent current in the supply cable.

Frequently asked

Which target cos φ should I choose?

Grid operators usually require at least 0.90; designing for 0.95 is common. Compensating to 1.0 is mostly uneconomic and can lead to capacitive operation at partial load.

Can I overcompensate?

Yes. Overexcited operation – capacitive reactive power fed into the grid – is also objected to by grid operators and can cause voltage rise. That is why varying loads use controlled compensation.

Calculating is the easy part.

A formula gives you a number. Designing a plant also demands installation method, grouping, discrimination, the standards in force and a look at the installed base. That is what we take on.

Request a project

Contact

Tell us what it is about.

A phone call or three lines is enough. From the very start you talk to the people who will later work on your project – not to a distribution list.

Direct

Locations

Head officeStellmacherstr. 7
33428 Marienfeld (Harsewinkel)
Gütersloh officeWagenfeldstr. 2
33332 Gütersloh

Or write to us

We usually reply within one working day.

Go to the contact form