The most expensive decisions in electrical engineering are made before the first schematic exists. In basic engineering, a change costs one line in the specification. In detail design it costs pages. On site it costs days, and sometimes a shutdown.
This becomes particularly clear with plants built in modules. Mechanics, manufacturing, electrical engineering and final assembly take place separately in space or organisation, often at different suppliers. Mechanically, the plant is built in modules. Electrically, it still has to be thought through as one plant.
What is basic engineering?
Basic engineering is the phase in which the fundamental technical decisions about a plant are made before detail design begins. For electrical engineering this means voltage levels, infeed, protection concept, safety architecture, module boundaries and designation system are fixed. The results are the specification, overview diagrams, load lists and the structures on which detail engineering builds.
In detail engineering these become schematics, terminal and cable plans, the cabinet layout and parts lists. Whatever stays open in basic engineering has to be made up there, at a higher cost.
Four phases, one continuous thread
| Phase | What is created there |
|---|---|
| Concept engineering | electrical master plan, load balance, medium- and low-voltage levels, module boundaries |
| Basic engineering | specifications, supply concept, standards, single-line diagram, load list, interface control document, network architecture |
| Detail engineering | MCC and I/O engineering, schematics, for example in EPLAN Electric P8, safety engineering to PL or SIL |
| Implementation | manufacturing, installation, FAT and SAT, commissioning, redlining, as-built documentation |
We do not carry out manufacturing, installation and commissioning ourselves. On request, we bring in specialised partners and coordinate the interfaces. We keep the documentation up to the as-built state, so that the drawings end up showing what was actually built.
Five decisions on energy
1. Electrical module boundaries. Where does a module end electrically? This determines which control cabinet supplies what and which cables cross a module boundary. If the boundary is only drawn during detail design, it often ends up where it suits the mechanics, not where it makes electrical sense.
2. Supply points. Where does energy enter which plant area? The answer determines cable routes, protective devices and whether a fault in one area takes neighbouring areas down with it.
3. Power reserves. How much reserve do the incoming supply, distribution boards and control cabinets get? Without a defined reserve, every extension turns into a new incoming supply.
4. Voltage levels. Which level is distributed where, from medium voltage down to control voltage? This fixes transformers, distribution and protection concepts long before the first device is selected.
5. Earthing and equipotential bonding. System type, earthing concept and equipotential bonding can hardly be retrofitted once the plant is standing. And they help decide whether communication and drives will later run without interference.
Three decisions on control and safety
6. Control architecture. Central or distributed, one controller per module or one for everything? This choice determines how inputs and outputs are distributed and how many control cabinets there are.
7. Communication networks. Fieldbus and Ethernet, topology, segments, the boundary between production and office network. A network that grows with the plant without a plan behind it becomes expensive during troubleshooting.
8. Safety architecture. Which safety functions are there, which areas shut down together, which performance level or SIL is required? This has to be settled before detail design, because afterwards every change runs through schematics, control and verification.
Three decisions at the interfaces
9. Cable handovers. Who lays which cable, and where is the handover? At module and supplier boundaries, this is the most frequent source of gaps and duplicated work.
10. Plug and connection concepts. Are modules connected by plug connectors or hard-wired? Pluggable handovers make pre-testing and installation faster, but have to be planned from the start.
11. Delivery and scope boundaries. Who supplies control cabinets, field installation and software, and where does each scope end? Unclear boundaries almost always mean that part of the work is done twice or not at all.
Two decisions on standards
12. Designation system. How are function, location and device designated? Anyone who only settles this during design ends up re-designating several times. What such a structure looks like is explained in Reference designations in EPLAN.
13. Technical standards. Component standard, norms, CAE standard with article master data and macros. A standard that exists before the project makes every further project faster. Why this counts especially in EPLAN is explained in EPLAN macros and templates.
Starting early pays off
External electrical design often only starts with detail design. The decisions before that are then made by someone else, or they are made in passing. On request, we come in earlier. We contribute to the electrical concept and basic engineering and coordinate the interfaces between mechanics, process engineering and electrical engineering. Our experience for this comes from projects in steel, intralogistics, the process industry and energy.
What this looks like as an overall project with one contact is described in our project support. The detail design afterwards we take on in electrical design, in EPLAN, ELCAD or WSCAD.