Steel production

Modernisation of one of Europe's largest blast furnaces

System migration of a plant with 11,000 measuring points in just 120 days, under extreme time pressure and alongside ongoing production planning.

11,000
Measuring points
850
Drives
220+
Control cabinets
120
Days to completion

Challenge

A large European steel producer modernised its blast furnaces. The goal was the comprehensive integration of new control systems, including dismantling, rebuilding and commissioning within just 120 days, to avoid long downtimes. Preparation alone took around a year.

Our contribution

Our teams worked into the plant directly on site. We produced the specifications, carried out the electrical engineering design in EPLAN and used our generator tool. A change management tool we developed ourselves ensured planning reliability and cost transparency throughout.

Result

The system migration of a plant with 11,000 measuring points, 850 drives and more than 220 control cabinets was completed within the extremely tight schedule. This significantly improved operational stability and the precision of production control, and created the basis for further optimisation.

Contact

Tell us what it is about.

A phone call or three lines is enough. From the very start you talk to the people who will later work on your project, not to a distribution list.

Direct

Or write to us

We usually reply within one working day.

We only use your details to answer your enquiry. More in our privacy policy.

Go to the contact form

Olaf Kreith

Your contactOlaf KreithHead of Sales

Quick question

Do you need help or have any questions?

Tell us briefly what it is about. We usually reply within one working day.