Steel production
Modernisation of one of Europe's largest blast furnaces
System migration of a plant with 11,000 measuring points in just 120 days – under extreme time pressure and alongside ongoing production planning.
- 11,000
- Measuring points
- 850
- Drives
- 220+
- Control cabinets
- 120
- Days to completion
Challenge
A large European steel producer modernised its blast furnaces. The goal was the comprehensive integration of new control systems – including dismantling, rebuilding and commissioning within just 120 days, to avoid long downtimes. Preparation alone took around a year.
Our contribution
Our teams worked into the plant directly on site. We produced the specifications, carried out the electrical engineering design in EPLAN and used our generator tool. A change management tool we developed ourselves ensured planning reliability and cost transparency throughout.
Result
The system migration of a plant with 11,000 measuring points, 850 drives and more than 220 control cabinets was completed within the extremely tight schedule. This significantly improved operational stability and the precision of production control, and created the basis for further optimisation.
Contact
Tell us what it is about.
A phone call or three lines is enough. From the very start you talk to the people who will later work on your project – not to a distribution list.
Direct
- Phone+49 (0) 5247 4070-66
- Emailinfo@fisekon.com
- AvailabilityMon – Fri, 8:00 – 17:00 CET
Locations
33428 Marienfeld (Harsewinkel)Gütersloh officeWagenfeldstr. 2
33332 Gütersloh
Or write to us
We usually reply within one working day.