Modernising a weaving mill while production keeps running

Twenty identical looms, a hall distribution that has grown over decades and drawings from the past. How a modernisation succeeds without shutting down the hall.

3 min read

In this article
  1. The existing plant first, then the machine
  2. Twenty identical machines, one template
  3. Dust and heat in the cabinet
  4. More inverters, a different grid
  5. Converting row by row

In many weaving and spinning mills the machines stand in long rows. Twenty, thirty, sometimes more machines of the same type, connected to a hall distribution that has grown a little with every extension. The drawings often still exist only on paper, and not every change of recent decades made it into them. Anyone modernising here plans against two opponents at once, the unclear existing state and the running production.

The existing plant first, then the machine

Before the first machine is touched, there is the survey. Which sub-distribution supplies which row, where are busbars and outgoing feeders, what hangs on which fuse? The old paper drawings are compared with the hall and turned into digital documentation that can be maintained afterwards. How that works is described under Legacy drawing digitisation.

Only with this state can one reliably say which machines can be converted together and which sections of the hall can keep running meanwhile.

Twenty identical machines, one template

The biggest lever in the textile industry lies in repetition. Where many machines of the same type stand, a clean template pays off once and then saves time on every single machine. Macros for the machine, its supply and its connection to the control system turn twenty individual drawings into a system.

That includes uniform designations, so that maintenance finds the same logic in every machine. Why we usually continue the existing scheme in existing plants rather than replacing it is explained in IEC 81346 designations need a system, not just the standard.

Dust and heat in the cabinet

Fibre fly is the silent enemy of every control cabinet in the textile industry. Fans with filter mats draw in fibres, the filters clog, the temperature in the cabinet rises. New drives with frequency inverters also give off more heat than the old technology. How much heat an enclosure has to dissipate, and whether fans are still enough or a closed cooling concept is better, can be calculated beforehand, for example with our enclosure cooling calculator.

More inverters, a different grid

When many machines move to modern drives, the picture in the hall’s supply changes too. Inverters create harmonics and change the reactive power demand. A compensation system sized twenty years ago for induction motors on the grid may then no longer fit. Our reactive power compensation calculator gives a first assessment. If a new supply is added, the short-circuit current also needs a fresh look, as described in Initial symmetrical or peak short-circuit current?

Converting row by row

Whether a modernisation succeeds without any downtime depends on the hall. What can be planned is the sequence. We define the conversion steps so that only one machine group stops at a time while the rest keeps producing. Every group gets the same template, the same designations and the same documentation. In the end the hall has not only new drives but documents that maintenance can rely on.

How we approach existing plants in general is described under Modernisation of existing plants.

André MeschkatWritten by André Meschkat, Office Manager

FISEKON newsletter

When there is something new that genuinely helps.

We write when a new calculator is ready, an article on electrical engineering design is published or there is news from the FISEKON world. Not more often.

  • About four to six issues a year.
  • Unsubscribe any time with one click.

After submitting you will receive an email with a confirmation link. Only then are you subscribed. This ensures nobody can enter someone else’s address.

Unsubscribe from newsletter

Contact

Tell us what it is about.

A phone call or three lines is enough. From the very start you talk to the people who will later work on your project, not to a distribution list.

Direct

Or write to us

We usually reply within one working day.

We only use your details to answer your enquiry. More in our privacy policy.

Go to the contact form

Olaf Kreith

Your contactOlaf KreithHead of Sales

Quick question

Do you need help or have any questions?

Tell us briefly what it is about. We usually reply within one working day.